Overdue
4
This week
5
All
34
Your milestone progress
9 of 17 assigned milestones complete this quarter
53%
Overdue
4 milestones
Cut over bastion-prod-02 to AL2023 image
POAM-0142
Jul 12 · 25d late
Critical
3
RK
Extend audit log retention to 12 months
POAM-0121
Jul 28 · 9d late
High
TN
Document the compensating control for CP-9
POAM-0170
Aug 1 · 5d late
Moderate
DM
Chase 3PAO on the Q2 assessment schedule
POAM-0147
Aug 4 · 2d late
Vendor dependency
RK
Next 7 days
5 milestones
Apply hardened TLS policy to public LB
POAM-0155
Aug 9 · in 3d
High
MP
Collect Q2 recertification attestations
POAM-0163
Aug 12 · in 6d
Moderate
2
JB
Credentialed rescan and evidence capture
POAM-0142
Aug 15 · in 9d
Critical
MP
Completed recently
See all
Cut over bastion-prod-01
POAM-0142
Completed Jul 9
RK
Approve change request CHG-4471
POAM-0142
Completed Jul 2
DM
Cut over bastion-prod-02
Milestone of
POAM-0142
25 days late.
The window slipped twice for unrelated incident response.
Status
In Progress
Not Started
Blocked
Complete
New due date
Reason for the change
Incident response conflict
Awaiting vendor
Resource constraint
Change window unavailable
Attach
Comment
Save changes